Skip to content
Just Enough Build

Concrete Footing Calculator

Work out the concrete for deck-style footings, a square pad with a round pier on top or pads on their own, in cubic yards and bags.

Formula and worked example below

1. Footing type
2. Measurements
in

Each side of the square pad at the bottom

in
in

Size of the form tube

ft

From the top of the pad to the top of the pier

%

The concrete industry (NRMCA) advises ordering at least 4–10% extra. Running short mid-pour is worse than a few spare bags.

4. Bag size

Footing sheet

6 footings: 24 in pad × 12 in, 10 in pier × 4 ft

Concrete to order

1.51yd³

Includes 10% extra

Each footing
6.18 ft³
Net volume
37.1 ft³ · 1.37 yd³
With 10% extra
40.8 ft³
Metric equivalent
1.16 m³

68× 80 lb bags

or 91 × 60 lb · 109 × 50 lb · 136 × 40 lb

Each 80 lb bag makes about 0.60 ft³ of concrete.

Not to scale. 6 footings: 24 in pad × 12 in, 10 in pier × 4 ft

Shopping list

  • 6880 lb bags of concrete mix0.60 ft³ per bag
  • 6Form tubes, 10 in diameterAt least 4 ft long each

How it's calculated

A deck footing is usually two shapes: a flat square pad at the bottom that spreads the load, and a round pier (often poured in a cardboard form tube) that brings it up to the post. The calculator adds the two, then multiplies by the number of footings.

Pad (ft³)        = Pad width × Pad width × Pad thickness   (inches ÷ 1,728)
Pier (ft³)       = π × (Pier diameter ÷ 2)² × Pier height
Each footing     = Pad + Pier
To order         = Each × Number of footings × (1 + Extra % ÷ 100)
Bags             = To order ÷ bag yield, rounded up

Worked example

Imperial

6 footings: 24 in × 24 in × 12 in pad, 10 in × 4 ft pier

Pad
2 × 2 × 1 = 4.00 ft³
Pier
π × (5/12)² × 4 = 2.18 ft³
× 6
37.09 ft³ = 1.37 yd³
+10%
40.80 ft³ = 1.51 yd³
80 lb bags
40.80 ÷ 0.60 → 68

Metric

6 footings: 600 × 600 × 300 mm pad, 250 mm × 1.2 m pier

Pad
0.6 × 0.6 × 0.3 = 0.108 m³
Pier
π × 0.125² × 1.2 = 0.059 m³
× 6
1.001 m³
+10%
≈ 1.10 m³

Tips

Check your local code first.

Footing size and depth are set by your building code, soil and the load on the deck. This tool calculates concrete; it does not design footings.

Count every footing. Include footings for stairs and any extra posts under a hot tub or pergola, not just the main deck grid.

Buy tubes a little long. Form tubes are cut to length on site. Buy them long enough to reach from the pad to above grade.

Questions

How much concrete for a deck footing?

Add the pad and the pier. A 24 in square pad 12 in thick is 4 cubic feet; a 10 in pier 4 ft tall adds about 2.2 cubic feet. So each footing needs about 6.2 cubic feet, and six of them need 37 cubic feet (1.37 cubic yards) before extra.

How do I calculate concrete for a form tube?

A form tube is a cylinder: π × (diameter ÷ 2)² × height. A 10 in tube 4 ft long holds π × (5 ÷ 12)² × 4 ≈ 2.18 cubic feet, a little under four 80 lb bags. Choose "Pad + pier" and set the pad to zero if you only have the tube.

What size should my footings be?

Footing size depends on the load, your soil and your local building code, and many areas require a permit for deck footings. This calculator works out the concrete for the size you choose; it does not size footings for you. Check with your local building department.

Should the pier go below the frost line?

In cold climates codes usually require the bottom of footings to sit below the local frost depth, which varies by area. Your local building department can tell you the required depth. Enter the full pier height you plan to pour, including the part below ground.

Sources

Bag yields come from manufacturers' own data sheets. The 80, 60 and 40 lb yields match across two manufacturers. Metric bags are calculated at the same yield per kilogram as the US bags. That gives about 9.4 L for 20 kg, 11.7 L for 25 kg and 14 L for 30 kg, which falls within the figures published for those bag sizes below. Yields vary by brand and product, so the one printed on your bag always wins.

  1. QUIKRETE, Concrete Mix (No. 1101) data sheet. Yields: 40 lb ≈ 0.30 ft³ (8.5 L), 50 lb ≈ 0.375 ft³ (10.6 L), 60 lb ≈ 0.45 ft³ (12.7 L), 80 lb ≈ 0.60 ft³ (17 L).
  2. SAKRETE, High Strength Concrete Mix data sheet (rev. 7-10). Yields: 40 lb .30 cu ft, 60 lb .45 cu ft, 80 lb .60 cu ft.
  3. SAKRETE, 5000 Plus Concrete Mix data sheet. Yield: 50 lb (22.7 kg) bag 0.38 ft³ (0.011 m³).
  4. National Ready Mixed Concrete Association (NRMCA), Concrete in Practice CIP 8: Discrepancies in Yield (2016). Order more than the original volume estimate by at least 4 to 10 percent to cover waste, extra thickness and form deflection.
  5. NIST, Guide to the SI (SP 811), Appendix B.8: Factors for Units Listed Alphabetically. 1 ft = 0.3048 m and 1 in = 0.0254 m exactly; 1 yd³ = 0.764 554 9 m³.
  6. SAKRETE Canada (King Packaged Materials), Concrete Mix product data sheet. Yield: 30 kg (66 lb) bag ≈ 0.014 m³ (1/2 ft³).
  7. Easy Mix (River Sands), Super Strength Concrete technical data sheet. Each 20 kg bag contains approximately 10 litres of concrete; test results list a volume yield of about 9 litres.
  8. Cement Australia, Concrete Mix 20 kg sell-in sheet. Two 20 kg bags cover a 450 × 500 mm slab about 75 mm thick, which works out to about 8.4 litres per bag.
  9. Firth (Dricon), CivilCrete technical data sheet. Yield per 25 kg bag: 0.010 m³ (approximate).
  10. CMI, G25 Concrete Mix data sheet. A 25 kg bag produces approximately 0.012 m³ of finished concrete.

Sources checked 21 November 2026.